Exploring Toronto’s new BMX supercross

The approach
This project was extremely challenging, requiring significant site servicing work, precise and complex earthwork for the track course, and similarly precise forming of the reinforced concrete start ramps and fabrication of the start gate screening. The challenge was heightened by the requirement to carry out this work throughout the winter of 2014/15 for a spring completion to achieve UCI certification and test events in advance of the Pan Am Games.
This planning of this unconventional project was addressed through an unconventional process. The design team considered various materials and researched the recent history of these facilities throughout the world and in Olympic contests.
The esthetics of concrete allowed the practical considerations of storage, ramp heights, and retaining wall sections to each be expressed as architectural elements within a single form. Board-formed concrete, prefinished concrete masonry units (CMUs), and smooth-faced framing members all add to the distinct language of each element—at once separate and unified.
The solidity of the concrete base structure is offset by the lightness of the superstructure constructed entirely of hot-dip galvanized piping that form the guards at landings and the overhead structure shading the start gates. The overhead structure also incorporates continuous linear light-emitting diodes (LEDs) within the piping.

Challenges
Gateman-Milloy employed several strategies to meet the completion date, including the negotiation of an overtime regime with the client and architectural concrete trade to accelerate the schedule during the seasonable fall weather. It also proposed a non-vibratory compaction methodology for backfilling the ramp retaining wall prior to concrete reaching 75 per cent strength, as well as utilizing a high-early-strength concrete mix design to accelerate the 75 per cent strength.
With a severely compressed schedule, portions of the work had to be completed during the winter. To allow work to continue, winter protection measures were implemented from December through March. These included heating, tarping, and employing weather mixes for concrete curing.
Other challenges encountered on the project included paving the three 180-degree track turns and placing asphalt on slopes of 1:1 or steeper. The 5-m (16-ft) wide elite ramp, on a 28-degree slope, had to be poured in December with a specific depth broom finish. Since the ramp was a suspended slab, there was no adjacent surface from which to stage—this meant the use of booms to complete the broom finish.
Apart from the tight deadline, the biggest construction challenge facing the team was the location of the venue. The site of the track had been selected early on in the city’s planning process, even before the design team was engaged. As soon as design and construction planning began, the site was found to be a low point of the park; further, its drainage catchment area was enormous.

Building a dirt track on what was essentially a wetlands area required an extensive underground drainage system. Flows had to be managed to allow the track to be dry within 30 minutes of a rainfall (one of the criteria for the games), and the water quality had to satisfy the requirements of the Toronto Region Conservation Authority (TRCA) and Ministry of Natural Resources (MNR) because a designated wetland area lies immediately to the south of the site.
Conclusion
The BMX Supercross Track Legacy Project has been identified as one of the top five projects in the world for 2015 by ArchDaily in the International Sports Architecture category. Internationally, it was featured in Designlines, Dezeen, and Designboom magazines—the third publication declared it “an object in a landscape, and a landscape in its own right.” It served as the backdrop to the CBC national broadcast of Pan Am Day in Canada, hosted by Scott Russell.
Perhaps most importantly, it has been lauded by those riders who have used it. World number-two rider, Olympian, and eight-time Canadian Champion Tory Nyhuang, who claimed the gold at Pan Am, called it “an awesome track” while Cycling Ontario head coach Brenden Arnold referred to it as a “game-changer.” Most promising for lovers of BMX racing, Hannah Parish of Cycling Canada has predicted “this facility will one day produce an Olympic champion.”
There were two primary challenges facing the construction of the Toronto project—timing and long-term use. The deadline was met in spite of the many challenges, and the facility has a bright future ahead, both because of its architectural esthetic and its use as a world-class sporting venue.
Mike Dawson is the lead project manager of Gateman Milloy’s Site Development and Landscape Construction Division. A subject expert in landscape design and construction, he is at the forefront of applying new technologies and methodologies in his field. Dawson has more than 30 years of experience in estimating, project management, cost control, and site experience; he began as an assistant estimator and site administrator at the Expo’86 site in Vancouver in 1985. Dawson’s expertise includes work in major urban landscape, recreational landscape, and civil and environmental development projects. He can be reached via e-mail at mdawson@gatemanmilloy.com.