Recent technological advances have made it practical to deliver concentrated sunlight deep inside buildings. This new approach to energy-efficient lighting means almost all areas of a building can be illuminated whenever the sun shines without requiring any increase in floor-to-floor height or large expanses of glazing. As a result, core sunlighting has the potential to significantly influence how the building industry optimizes green building designs.

This article compares the performance of a core sunlighting system, in terms of energy savings and cost, to that of an alternate design using the standard daylighting strategies that have become common in green buildings. This comparison shows a building employing a core sunlighting system provides significant electrical energy savings at significantly lower capital cost per kWh/year saved.

It has become a building industry-wide challenge to illuminate interior spaces while consuming as little electrical energy as possible. Daylight, when used well, creates spaces most people find pleasant and healthy, and good daylighting delivers on the triple bottom line since saving energy is also economically and environmentally sound. There is no question daylighting is a desirable way to illuminate a building. The challenge is how best to do it.

The value of core sunlighting
Daylighting enters a building in numerous ways, including windows, light shelves, and skylights—these approaches offer good solutions for perimeter spaces. However, when these areas are brightly lit by natural light, increased electric lighting is often needed in the core to provide balanced illumination, so daylight at the perimeter can actually lead to greater use of electrical energy.

To mitigate this problem, sustainable buildings are often designed with narrow floor plates, high ceilings, and high fenestration ratios, as well as interior atria and courtyards, effectively eliminating the core. Such ‘macro’ building design solutions enable daylight to penetrate throughout the building, but they have several disadvantages.

For instance, they cannot address the need to reduce the energy consumption of existing buildings, many of which have large floor plates. They also may not work well with the specific site conditions, or with the building’s functional program requirements—a large, continuous floor plate may be necessary, for example. Moreover, there are trade-offs associated with maximizing daylight using large areas of glazing. More stringent thermal and glare controls are required, and these tend to increase complexity and reduce overall illumination quality.

In addition to such considerations, the most important concern with this approach boils down to cost—enlarging the perimeter is a more expensive way of illuminating the building since the construction cost per unit area of floor space is significantly increased. It could perhaps be argued that, in the absence of a better solution, this increased cost is warranted to save electrical lighting energy and provide the other benefits of daylight.

However, now that cost-effective commercial lighting systems that pipe sunlight deep into the core are emerging in the marketplace, a narrow, high-fenestration-ratio design is no longer the only way to fully daylight the space. The idea of core sunlighting is not a new one, (See Sustainable Building Technical Manual: Green Building Design, Construction, and Operations, a publication produced in 1996 by the U.S. Green Building Council (USGBC) and sponsored by the U.S. Department of Energy (DOE) and the U.S. Environmental Protection Agency [EPA]). but new optical materials and designs make this concept practical and affordable. (Visit www.phas.ubc.ca/ssp/CoreSun_index.html[2] for more information). Recent demonstration systems have shown concentrated sunlight delivered into the building core significantly reduces the energy used for electric lighting and illuminates the space with a lighting quality most people prefer.

Core sunlighting involves harvesting sunlight at the perimeter of the building, moderately concentrating it, transporting it into the building, and controllably releasing it deep inside as illumination. Significant electrical energy savings can be achieved by incorporating automated lighting controls that turn off the supplemental electric lights whenever adequate sunshine is available.

A properly designed core sunlighting system can deliver illumination that has the advantages of high-quality electric lighting while also providing the benefits of daylight, including excellent colour-rendering properties and a greater sense of connection to the outdoor environment. Since the windows are no longer required to provide all the daylighting in the space, they can be sized appropriately to focus on the desired views while optimizing building envelope environmental control.

An example of a core sunlighting system. Image courtesy Willie Dean, Glumac[3]
An example of a core sunlighting system.
Image courtesy Willie Dean, Glumac

The challenge of cost
The most challenging issue that has arisen in the area of core sunlighting is one that is fundamentally important (and often overlooked) with most solar technologies—that of up-front capital cost. To be successful, core sunlighting solutions must use optimized, cost-effective materials and volume manufacturing techniques so as not to significantly increase the price of any of the other building components.

The capital investment in any building system is dominated by the structure itself, which means a real expense must be attributed to each cubic metre of space within a building and each square metre of its surface area. This leads to the conclusion any daylighting approach intended to save energy (and therefore, money) has an effective additional capital cost determined by the volume and surface area of the building it occupies.

From this perspective, conventional daylighting approaches requiring increased floor-to-floor spacing may not provide a commensurate net economic benefit in terms of the resultant energy savings. In contrast, concentrated sunlight piped inside the already existing plenum requires much less space and, therefore, does not share the same capital cost burden. It is important to emphasize this conclusion only applies to passive daylighting for core spaces. Daylighting in perimeter spaces using windows and skylights is a practical and cost-effective approach, particularly if it is employed in combination with core sunlighting systems to form a complete natural lighting system for the building.

Two demonstration installations in British Columbia. Images courtesy SunCentral[4]
Two demonstration installations in British Columbia.
Images courtesy SunCentral

A practical approach
Cost-effective core sunlighting technologies are emerging, and one system in particular has shown the potential for cost effectiveness. This approach, invented at the University of British Columbia (UBC), uses a sunlight concentrator to collect and concentrate the sunlight, and a hybrid light guide for distributing it inside the building.

The concentrators are incorporated into the façade above the windows and housed in a protective enclosure. To capture the sunlight, small mirrors move in unison to track the sun’s motion throughout the day. Once the sunlight has been redirected by the automated mirror array, it is concentrated by about a factor of 10—sufficiently concentrated to substantially reduce the space required within the building for distribution, but not so concentrated as to pose any possibility of a fire hazard.

The concentrated sunbeam is then directed through a small window in the exterior wall and into the specially designed hybrid light guides, which are integrated with dimmable electric lamps and sensors that monitor the illumination level so the sunlight can be supplemented when required (Figure 1).

Two recent demonstration systems, funded by federal and provincial government grants and a consortium of industry partners, have been installed in buildings in the Vancouver area to show the technology can be seamlessly integrated with standard construction techniques (Figure 2). Preliminary verification indicates the performance matches the predictions that were generated using historical weather data for the region. Long-term verification of the energy savings and occupant experience surveys are ongoing.

Buildings A, B, and C— also discussed in Figure 4— have the same net area of leasable space, but use different methods of illumination.[5]
Buildings A, B, and C— also discussed in Figure 4— have the same net area of leasable space, but use different methods of illumination.

The system has been highlighted to show the concept of core sunlighting is no longer just a theoretical possibility, but rather it is now a practical and affordable daylighting alternative. Other technologies currently under development elsewhere may also prove to be viable and the authors anticipate the emergence of a thriving new industry centred around the concept of core sunlighting.

Comparison to a more conventional approach
With these demonstration systems as evidence that core sunlighting is now practical, the authors carried out a design study to compare the capital cost, operating cost, and energy use in three representative buildings that have the same net area of leasable space, but use different methods of illumination.

Building A, the base design, has standard floor-to-floor spacing and is designed with solid walls (R-14 [i.e. RSI 2.47]) and standard double-glazed strip windows (R-1.6 [i.e. RSI 0.28]) at a height of 750 to 2100 mm (30 to 83 in.) above the floor. The windows provide a modest amount of daylighting in the perimeter spaces, but most of the lighting is provided by electric lights.

In contrast, Building B has increased floor-to-floor spacing and a ‘full-height’ glazed envelope to enable deep daylight penetration. It has a reasonably high-performance curtain wall system consisting of low-emissivity (low-e) coated, argon-filled, double-glazed units, with thermally broken aluminum frames. The spandrel extends at each floor level from 750 mm above the finished floor down to the underside of the ceiling below. The spandrel is assumed to have an insulation value of R-12 (i.e. RSI 2.11), while the glazing portion is assumed as R-5 (i.e. RSI 0.88) (resulting in a combined value for the spandrel and glazing of about R-6 (i.e. RSI 1.06). Due to the high ceilings and fenestration ratio, the electric lights in Building B need only be operated when daylight is not available.

Building C is identical to Building A, but it incorporates a core sunlighting system that enables the electric lights to be turned off whenever the sun shines. Figures 3 and 4 compare the design details for the three buildings.

Design details for the three comparison buildings.[6]
Design details for the three comparison buildings.

Cost and energy analysis
For the purpose of this cost and energy analysis, the authors present data based on the climatic conditions for Chicago, since it is representative of a typical city that experiences fairly hot summers and fairly cold winters. (They have also carried out the same analysis for Vancouver, which has a more temperate climate. While the numbers are somewhat different, the overall conclusion remains the same.)

To determine the capital cost for each building, the authors used a common construction costing analysis that is standard industry practice at the feasibility and conceptual design phases. This approach employs an assembly cost estimation to determine the cost per square metre for the construction assemblies, and further unit cost input from a large local construction firm. They used a building information modelling (BIM) program to model the buildings and generate the main assembly schedules and areas, and the unit costs were applied to obtain assembly costs. (Visit www.usa.autodesk.com/revit-architecture[7]). Then they applied the city cost indexes to adjust these costs for Chicago (about five per cent higher than Vancouver). (All monetary figures in this article have been converted into Canadian currency).

Since core sunlighting systems are in an early stage of development, comprehensive cost data is not available at this time. For the purpose of this analysis, the authors estimated Building C would incorporate 10 sunlight concentrators, each 3 m (9.9 ft) wide, on every floor on the south façade of the building, for a total of 60 concentrators, each having a total installed cost of $1500. This increased the cost of the lighting for Building C by $90,000 above Building A, but there were no other changes to the cost as a result of the core sunlighting system. (The cost per concentrator used in this analysis represents a reasonable target for a cost-effective core sunlighting system manufactured in modest industrial volumes of 1000 monthly) The anticipated capital costs for each building are summarized in Figure 5.

Cost case study for Chicago.[8]
Cost case study for Chicago.

Next, the authors considered the energy use in each building, and again implemented the available practice tools commonly used at the feasibility/conceptual design phase. Energy analysis software (Visit www.greenbuildingstudio.com[9] for more information). was used with the building models to calculate the energy requirements for each building using the regional climatic database for Chicago and a specified occupancy profile (i.e. process load) common to all three buildings. The program calculates the annual energy requirements for the building, in terms of electrical (i.e. lights, HVAC electrical equipment, exterior loads, and miscellaneous equipment), and fuel use for space heating and hot water.

A core sunlighting system is not yet an integrated option in these software packages. To account for the energy savings in Building C as a result of the core sunlighting system, the authors reduced the electrical energy required for lighting by 30 per cent of the value that was calculated for Building A. This value was determined using the approximate direct sunshine probability of 50 per cent (taken from historical weather data for Chicago), (For annual sunshine hours in Chicago, visit www.rssweather.com/climate/Illinois/Chicago[10]). and the approximate fraction of Building A that was illuminated solely by electric lights (60 per cent).

Energy use in each building type in Chicago.[11]
Energy use in each building type in Chicago.

The electrical energy required for space cooling was reduced by 12 per cent to account for the reduction in heating load associated with turning off the electric lights half the time during the summer. Similarly, the fuel required for space heating was increased by two per cent, to account for the decrease in heating load during the winter. The energy intensity values calculated for the three buildings are shown in Figure 6. (These values are reasonable compared to the average value for office buildings in Canada, which is about 1.2 GJ/m2/year.)

The authors then calculated the simple economic payback time, based on the capital cost and the operating cost, for Buildings B and C, compared to the base design of Building A. (The operating cost was calculated using the annual energy use above, using an electrical energy cost of $0.139/kWh and a fuel cost of $9.53/GJ.) (Recent electricity and fuel costs for Chicago can be found at www.bls.gov/ro5/aepchi.htm[12]). These comparisons, along with the annual energy savings, are provided in Figure 7.

Figure 7 illustrates the conventional daylighting design results in about twice the energy savings of that achieved by the core sunlighting system, but it costs 20 per cent more than the basic design, whereas the core sunlighting system costs only one per cent more. This suggests as new core sunlighting systems become available, they will be the most cost-effective method for daylighting buildings.

Estimated payback time for Buildings B (above) and C (below).[13]
Estimated payback time for Buildings B (above) and C (below).

Implications for the green building industry
Daylighting and occupant comfort present conflicting challenges in green buildings—a high fenestration ratio is desirable for bringing in natural light, but large expanses of glazing result in undesirable solar gain at some times of the year and loss of heat at other times. Furthermore, the incremental cost that is associated with higher floor-to-floor spacing, increased glazing, and increased perimeter area is often not justified by the resulting energy savings, and the simple economic payback time tends to be unreasonably long.

With practical core sunlighting systems coming onto the market, buildings can be daylit at a reasonable cost. The comparison of the three representative buildings shows though the conventional daylighting design can save twice as much energy as the one incorporating core sunlighting, it costs about 20 times as much.

Additionally, the core sunlighting approach overcomes many of the inherent conflicts with thermal comfort and glare that conventionally daylit buildings face, by enabling more modest fenestration ratios and directing sunlight downward from the ceiling in a glare-free manner. Consequently, with the advent of these new systems, an optimal method for daylighting buildings under most circumstances will involve a combination of core sunlighting in deep spaces and conventional daylighting near the perimeter.

Lorne Whitehead, PhD, P.Eng., is a professor at the University of British Columbia (UBC). He is the Natural Sciences and Engineering Council of Canada (NSERC)/3M Company Industrial Research Chairholder in Applied Physics and the chair of the Board of Directors of SunCentral. Whitehead is a member of the Illuminating Engineering Society of North America (IESNA) and has 27 years of experience in illuminating engineering. He can be contacted via e-mail at lorne.whitehead@ubc.ca.

Donald Yen, MAIBC, MRAIC, is a registered architect in British Columbia and Washington, and has 24 years of experience in the profession of architecture and sustainable design. He instructs in the areas of sustainable urban development and architectural and a structural computer-aided design and drafting (CADD) and graphics at the B.C. Institute of Technology (BCIT). Yen can be reached at donald_yen@bcit.ca.

Robert Salikan, MAIBC, AAA, MRAIC, is a principal at Salikan Architecture, a firm established in 1988, with projects in British Columbia, Alberta, the United States, and Japan. He is a registered architect in British Columbia and Alberta, and has 30 years of experience in architecture. Salikan can be contacted at robert@salikanarchitecture.ca.

Endnotes:
  1. [Image]: https://www.constructioncanada.net/wp-content/uploads/2016/02/Sun_UBC-exterior-2.jpg
  2. www.phas.ubc.ca/ssp/CoreSun_index.html: http://www.phas.ubc.ca/ssp/CoreSun_index.html
  3. [Image]: https://www.constructioncanada.net/wp-content/uploads/2016/02/F1-2.jpg
  4. [Image]: https://www.constructioncanada.net/wp-content/uploads/2016/02/F2-2.jpg
  5. [Image]: https://www.constructioncanada.net/wp-content/uploads/2016/02/F3-1.jpg
  6. [Image]: https://www.constructioncanada.net/wp-content/uploads/2016/02/F4-1.jpg
  7. www.usa.autodesk.com/revit-architecture: http://www.usa.autodesk.com/revit-architecture
  8. [Image]: https://www.constructioncanada.net/wp-content/uploads/2016/02/F5.jpg
  9. www.greenbuildingstudio.com: http://www.greenbuildingstudio.com
  10. www.rssweather.com/climate/Illinois/Chicago: http://www.rssweather.com/climate/Illinois/Chicago
  11. [Image]: https://www.constructioncanada.net/wp-content/uploads/2016/02/F6.jpg
  12. www.bls.gov/ro5/aepchi.htm: http://www.bls.gov/ro5/aepchi.htm
  13. [Image]: https://www.constructioncanada.net/wp-content/uploads/2016/02/F7.jpg

Source URL: https://www.constructioncanada.net/core-sunlighting-technology-offering-a-new-approach-to-green-building/