Assignment of design to constructors: A discussion and direction

by nithya_caleb | December 21, 2018 9:06 am

Images courtesy Dialog[1]
Images courtesy Dialog

by Keith Robinson, RSW, FCSC, FCSI, Cameron Franchuk, P.Eng., and Gerald Murnane

This article is published in three parts. The first part deals with identification of issues and concerns in communicating the need for design solutions during construction. The second part deals with different approaches to describing how to manage the deferred design process. Both articles draw attention to the “elephant” in the room and issues causing disruption and disagreements in executing this requirement.

The concepts identified are not new. Complexity of design is driving an increase in the quantity of specifications dealing with the deferred design process. The authors recognize experience of design professionals varies greatly and may be contributing to confusion, misconceptions, and inconsistency for those parties involved with providing design solutions identified by the deferred design process.

Recent changes to professional design services and construction procurement have put pressure on expectations for completeness of construction documentation. Downward pressure on professional fees translates directly to a reduction in design effort to fully describe construction, and consequently, a transfer of responsibility for many design solutions to the constructor, essentially delaying or deferring design responsibility to the construction phase of the work.

This deferral of design occurs separately from the production of construction documents, and is typically finalized by an entity other than the Registered Professionals of Record (RPR).

The Canadian Construction Association (CCA) recently identified disturbing trends indicating the professional design community in Canada is failing in its responsibility to provide complete and appropriate design solutions to the constructor, and consequently, is inappropriately transferring to project participants responsibility for design elements rightfully belonging to registered professionals.

The critical outcome of the CCA recommendations is a need for explicit communication to constructors from the RPR clearly and completely describing solutions presented within specifications that do not form a part of a firm’s standard services for engineering and design. Full acknowledgement of deferred design components is the responsibility of the RPR, with full disclosure to owners relating to the transfer of responsibility for certain design solutions to the constructor.

The CCA identified several reasons leading to the increased number of concerns associated with this practice, including a substantial decrease in design budgets, a lack of appropriate time to complete the design, and a reduction of the specialty design knowledge that does not normally form a part of traditional professional design responsibilities.

CCA indicated the subsequent decrease in quality of documents is not directly related to the quantity or effort to create extensive drawings and specifications from design professionals, rather it is a problem of the quality of communication within the whole of the construction documents. The association also indicated the use of computers and processes such as building information modelling (BIM) are implicated in the decrease in quality of documentation as users rely on imported information rather than creating project-specific content.

Part two and three of this article will address in greater detail concepts of delegation of design and design-assist—terms familiar to licensed professionals.

There is an opportunity for the community of design professionals to take leadership on this issue, and to act on necessary improvements to communications with the constructor within documentation by identifying appropriate risk appropriation and managing that risk to the benefit of the project and the owner. Ultimately, this controls exposure to liability arising from the responsibilities of the RPR. The authors believe concepts in this article can establish a standardized national understanding of issues surrounding deferred design, and an approach to reduce exposure to risk for design professionals and the construction community.

Collaborative or deferred design?

Figure 1: This table lists several forms of deferred design and the professionals involved.[2]
Figure 1: This table lists several forms of deferred design and the professionals involved.

Collaborative design requires the involvement of a supporting registered professional or supporting certified/qualified contributor for elements of design:

Collaborative design can be delivered using design‑assist process before bid through pre‑qualification or after bid as a cash allowance (Figure 1).

Design-assist before bid is typically obtained using a request for proposals (RFP) process in which the building elements and components are clearly defined by non-product specific performance attributes with a stated intent to form a contract with the successful collaborative design-assist partner, and which incorporates a methodology to return to open bidding opportunity if the design solutions process was not beneficial to project outcomes. This process is administered by the design professional and may entail early payment by the owner for design solutions that would otherwise occur during the construction period.

Design-assist after contract award can also be obtained via the RFP process during construction using similar documentation as described for the before-bid process, but administered through a cash allowance to recognize contractual obligation to identify design solutions that are not complete, and that will be determined during the construction period and administered by the constructor.

Deferred design is any design not completed in-house and represents specialist contributions not forming a part of the expertise of the RPR. Deferred design may involve solutions requiring engineering support from a supporting registered professional (delegated design) or non‑engineering solutions from a supporting certified/qualified contributor (assigned design).

Delegated-design solutions require specific input from a professional engineer retained by the constructor, supplier, fabricator, or manufacturer. The difference with assigned-design solutions is, while they also require specific input from a specialist retained by constructor, supplier, fabricator, or manufacturer, they do not require input from a professional engineer. There are components in the deferred design process that may require aspects of delegated and assigned design. These must be identified in the documents.

The deferred design process can include aspects of actionable and informational review of submittals, depending on the allocation of delegated design or assigned design, and which design profession discipline is involved with the aspect of the review. Deferred design may require the application of multiple submittal review stamps where two or more design professionals are involved with the review.

Full acknowledgement of deferred design components is the responsibility of the registered professional of record.[3]
Full acknowledgement of deferred design components is the responsibility of the registered professional of record.

Managing the deferred design and collaborative design process

Deferred design is completed by supporting registered professionals or supporting certified/qualified contributors who can provide supplementary supporting engineering, knowledgeable contributions, or architectural services for components of a defined discipline’s contribution during the construction phase of the project, provided they can submit appropriate assurances of their ability to design these components based on engineering provided by the design professional of record.

Collaborative design is similar in concept to deferred design, but occurs during production of the construction documents, where the supporting registered professionals’ contributions are fully incorporated by the RPR prior to the construction phase of the project.

Building codes in North America allow registered professionals of record to defer or assign design solutions for building components to “others” using appropriate delegation or assignment language through the contractual language and specifications. Transparency by the RPR is required to keep the owner fully informed regarding what design will be performed by themselves and what will be performed by others.

The one limitation under provincial state licensing guidelines is the co-ordinating professional of record and the registered professionals of record are not permitted to defer, delegate, or assign their responsibilities for compliance with the building codes; the responsibility for deferred or collaborative design remains with the co-ordinating professional of record.

Design intent versus design

Four forms of deferred design are listed in the table above.[4]
Four forms of deferred design are listed in the table above.

The phrases “design intent” and “design” are often used synonymously by registered professionals, as if they have the same meaning. Discussions arising from the concepts of deferred design require recognition of two separate functions associated with design intent and design.

Design intent represents the responsibility of registered professionals of record to the public regarding safety, and responsibility for incorporation of functionality and esthetics described by the owner’s stated performance requirements. Design represents the solution or outcome derived from the design intent. These words are used within this discussion to represent these two aspects and to maintain a clear distinction between the design intent responsibility of the design professional and the design solution responsibility of the constructor.

HISTORY OF COLLABORATION
Prior to the middle of the 19th century, there was a single role encompassing builder and designer. The separation between engineers, architects, and constructors evolved to what we now associate with modern construction practice: the arrangement of design responsibilities between licensed design professionals (e.g architects, engineers, and interior designers) and constructors (contractors, construction managers, and design-builders). Design professionals were respected and trusted to deliver on the full extent of the owner’s design brief. Constructors understood their contributions, using craftsmanship and intrinsic trade knowledge to provide expertise in interpreting the requirements described by the design brief.

 

According to the Canadian Construction Association (CCA), a decrease in design budgets, a lack of appropriate time to complete the design, and a reduction of the specialty design knowledge that does not normally form a part of traditional professional design responsibilities has resulted in a transfer of responsibility for many design solutions to the constructor. Photos © BigStockPhoto.com[5]
According to the Canadian Construction Association (CCA), a decrease in design budgets, a lack of appropriate time to complete the design, and a reduction of the specialty design knowledge that does not normally form a part of traditional professional design responsibilities has resulted in a transfer of responsibility for many design solutions to the constructor.
Photos © BigStockPhoto.com

The players and influencers

Most readers of this magazine are well aware of the traditional roles of constructor (contractor, construction manager, or design‑builder), and the architect/engineer (design professional, co-ordinating registered professional, or RPR).

The “other design entities” within the arena of professional involvement arising from the deferred or collaborative design process used to deliver deferred submittals during the progress of the work are not defined. Examples of these contributors have already been introduced as the supporting registered professional and the supporting certified/qualified contributors.

Supporting registered professionals are not mandated by the building codes, but delegation of design responsibilities to supporting registered professionals is a recommended mechanism—by most engineering associations—for the RPR to receive assurances from other registered professionals, who do not form a part of the project team and who can provide appropriate design solutions. Various professional associations at the provincial and state levels provide written guidance supporting the role of supporting registered professionals. The term used in this article may not match the definitions of those associations, but the concept of transference and acceptance of responsibilities is clearly described.

[6]The term “supporting certified/qualified contributors” is the “someone else entity” for deferred or collaborative design solutions not requiring participation by a registered professional. This term accounts for contributions from certified or qualified individuals to specialty components or specialist knowledge that does not form a part of the co-ordinating registered professional’s or RPR’s range of experience.

Contributions by the supporting certified/qualified contributors include design services associated with firestop design covered by a certified fire protection specialist (CFPS) and door hardware schedules and specifications provided by a door and hardware specification consultant (DHSC). This group may also include other certified individuals having specialty knowledge.

Provincial engineering associations only address:

The relationship between the RPR and assigned-design contributions by supporting certified/qualified contributors is not specifically described, although the concept is the same as required by the supporting registered professional described above.

Most architectural associations are silent on the concepts of supporting registered professionals and supporting certified/qualified contributors. This is the probable cause of inappropriate or incorrect deferred design that may be observed within the architectural project documents.

Deferring design must not be used to transfer design intent responsibility to the constructor because the RPR does not have sufficient time or budget to complete the design. Deferring design should only occur when the RPR does not have the necessary skills to complete the work, and the owner is informed and has accepted the need for deferral.

Owners have expectations of the RPR based on the fees paid; an expectation the RPR will provide a complete design, meaning any exclusions to the owner’s stated requirements are clearly identified prior to signing a contract with the owner.

Responsibilities of the constructor

Complexity of design is driving an increase in the quantity of specifications dealing with the deferred design process.[7]
Complexity of design is driving an increase in the quantity of specifications dealing with the deferred design process.

Design intent of temporary facilities has always been the responsibility of the constructor, including any engineering of temporary structures and safety systems not part of the primary building work. This responsibility does not form a part of the deferred design discussion; this is simply work the constructor does as a part of their contract deliverables. The design professional may ask to review these design components as an informational submittal, but responsibility stays with the constructor for these components. Engineering of temporary facilities is specifically excluded from the services provided by the RPR under normal contract requirements.

Forms of collaborative design

Collaborative design typically occurs during production of the drawings and specifications, but it can occur as a cash allowance component during the construction phase. It is generally incorporated as a component of the information contained within the construction documents, and requires no further delegation of design responsibility to the constructor.

Obtaining design solutions using a design-assist approach without compensation to the supporting certified/qualified contributors or the supporting registered professional demeans the value of those services and opens the RPR to scrutiny from peers if the design solutions fail to recognize the complexity of the project.

Collaborative design carries a responsibility for the RPR to maintain a competitive procurement process as well as recognize the professional’s responsibilities to the performance of the building as the co-ordinating professional of record/RPR.

The adage “you get what you pay for” is apt when obtaining design solutions from supporting certified/qualified contributors. The more complex the project requirements, the greater the need to pay for design-assist services.

DEFINITION OF ROLES
Registered professional: The entity defined by building codes as having responsibility for architectural, engineering, or interior design, and defined by provincial-level regulations and statutes as having professional responsibility for life and health safety for construction.

Co-ordinating professional of record: The entity responsible for engaging and coordinating the various registered professionals of record for design solutions required for the project, as defined by building codes.

Registered professional of record: The entity responsible for providing integral design and review of work specific to their area of discipline expertise, contributing to the whole of the project under the supervision of the
co-ordinating professional of record.

Supporting registered professional: Similar responsibilities as the registered professional of record. Services are obtained as a component of construction deliverables to provide professional engineering design solutions for components of work not part of the in-house expertise of the co-ordinating registered professional or the registered professionals of record.

Supporting certified/qualified contributors: Non-professional certified/qualified contributors providing specialist design solutions obtained as a component of construction deliverables. These contributors provide design solutions for components of work that do not form a part of the in-house expertise of the co-ordinating registered professional or the registered professionals of record.

 

 

INTEGRATED PROJECT DELIVERY APPROACH
Design solutions for engineered components are considered delegated design. In these cases, a contribution by a registered professional is required to complete the deferred design component, or the component is directly associated with building code compliance. This category includes items such as:

  • structural steel connections;
  • steel decking;
  • composite steel (owsj, heavy truss);
  • wind loadbearing studs;
  • light gauge loadbearing cold-formed framing;
  • stairs;
  • guard and handrail anchors to structure;
  • custom guards and handrails (non-pre-engineered systems);
  • composite wood (trusses, mass timber, glued-laminated [glulam] timber, etc.);
  • curtain wall anchors to structure;
  • custom curtain wall—themed or non-pre-engineered systems (this would be better forming a part of pre-construction design-assist category);
  • fall arrest anchors to structure;
  • fire suppression systems; and
  • seismic restraints for non-structural systems.

This list is not intended to be all-inclusive, and additional content will need to be considered for future development of delegated-design components.

Design solutions for specialty components are considered assigned design. A contribution by a registered professional is not required for code compliance, but certification or confirmation of properties is required. This category includes items such as:

  • concrete mix design;
  • door hardware (this would be better forming a part of pre-construction design-assist category);
  • firestopping;
  • skylights;
  • pre-engineered guards and handrails;
  • fall arrest systems (this would be better forming a part of pre-construction design-assist category, but is often dealt with as post-construction design-assist contribution);
  • standard pre-engineered systems;
  • custom canopies;
  • pre-engineered structures; and
  • integrated security systems (this would be better forming a part of pre-construction design-assist category).

 

Design-assist

Collaborative design typically occurs during production of the drawings and specifications.[8]
Collaborative design typically occurs during production of the drawings and specifications.

Collaborative design is identified as design-assist within many specifications prepared by the design community. It is similar in execution to delegated design and assigned design with respect to the requirements for letters of commitment and compliance. It is also similar in concept to what some describe as design-build. However, that description associates closely with a contractual condition, and should not be used to describe the actual approach to design-assist used for a project.

Design-assist is a procurement method by which, prior to completion of design, a construction contract may be awarded on a best-value basis where a specialty constructor provides design assistance to the design professional of record using a registered professional or supporting certified/qualified contributor retained using a RFP process.

Design-assist can be delivered using the constructor as a procurement entity when working with construction-managed or design-build methods of contract delivery.

Pre-construction design-assist is a fee-for-service approach to design solutions obtainable through a pre-qualification or RFP process. It provides for competitive procurement, with the final design solution forming a part of the construction documentation as either a “single-sourced with no substitutions” specification where design, products, and installation are included as an RFP requirement, or as basis-of-design products allowing for substitutions when only design solutions are provided (with a clause stating the design-assist entity will review proposed substitutions for conformance to the design during construction).

Post-construction design-assist requires the specification to be written in the form of a RFP, with expected construction costs managed as a cash allowance. The perception is market pricing will apply competitive influences on the outcomes, but experience shows post-procurement design-assist requires additional changes to adjacent assemblies because of the design solutions not being fully integrated or co-ordinated with the project.

Building codes in North America allow registered professionals of record to defer or assign design solutions for building components to “others” through contractual language and specifications.[9]
Building codes in North America allow registered professionals of record to defer or assign design solutions for building components to “others” through contractual language and specifications.

Design-assist is a collaborative process for developing acceptable shop drawings as a component of the construction documentation phase of the work. It follows a simple process: suggest → detail → refine (repeat until solution is derived) → implement → accept → construct.

The design-assist participant will be responsible for:

Shop drawings form a part of the construction documentation when prepared during the pre-construction phase. When prepared during the post-construction phase, full shop drawings are co-ordinated with construction documentation.

When properly executed, design-assist reduces design risk to the registered professionals of record, the supporting registered professionals, and the constructor, while providing price assurance to the owner.

The RPR retains responsibility of design in the design-assist process, similarly as to when working with other subconsultants forming a part of the total design work required for the project.

Conclusion

The authors hope the concepts in this article may contribute to an understanding of the issues surrounding deferred design. Now that some roles and duties have been defined, the authors will embark on a deeper discussion of responsibilities, engineering, submittals, and contract administration as they relate to deferred design in the next issue of Construction Canada.

References

Legal Interpretations

  1. New York State Professional Engineering Association: Practice Guidelines for Professional Engineers, Guideline 4 – Design Delegation, 2017.
  2. Johnston, Allison and Hord Law: Delegation of Design to Contractor, 2013.
  3. Ptizer Snodgrass: Liability for Delegated-Design, Understanding and Avoiding Risks to Design Professionals, 2013.
  4. SAFRAN Law Offices: The Dangers of Design Delegation, 2015.

Publications

  1. Revay and Associates Ltd.: The Revay Report, The Pitfalls of Incomplete Contract Documents, Volume 29, Number 1, 2010.
  2. Structure Magazine: CASE Business Practices, The Good and the Bad with Delegated-Design, 2017.

 

[10]Keith Robinson, RSW, FCSC, FCSI, has worked as a specifier since 1981, and is currently an associate at Dialog in Edmonton, Alta., responsible for research and development of technical specification content. His range of experience includes contract administration, building envelope detailing, and writing construction specifications. In addition to working on projects across Canada and in Egypt, Japan, and Costa Rica, Robinson also instructs courses for the University of Alberta, acts as an advisor to several construction associations and building trades committees, sits on several standards review committees for ASTM and National Fire Protection Association (NFPA), and is the Registrar for Construction Specifications Canada’s (CSC’s) Board of Directors. He can be reached at krobinson@dialogdesign.ca[11].

[12]Cameron Franchuk, P.Eng., is a structural engineer at Dialog, where he creates impactful spaces that build communities, but he wears many hats: engineer, educator, and mentor. Franchuk has a deep understanding of architectural concepts and building science. Integration of all disciplines is at the fore­front of his thinking throughout a project, from conception to completion. His work on low­-, medium­-, and high­-rise buildings, parkades, and pedways throughout Western Canada has helped shape communities. Franchuk can be reached at cfranchuk@dialogdesign.ca[13].

[14]Gerald Murnane is an associate, contract administration, with Dialog. He has been in the industry for 44 years both in Ireland and Canada. He joined Dialog in 1988. Murnane has an in-depth background in the design, specification, and management of complex construction projects. He is well respected in the industry for his senior construction administration expertise. Over the years he has built strong owner/contractor/designer team-based relationships and has a passion for resolving complicated issues as they arise. Murnane can be reached at gmurnane@dialogdesign.ca[15].

Endnotes:
  1. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/IMG_0020_N4_hiresjpg.jpg
  2. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/FIgure-1-defered.jpg
  3. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/EDIT_IMG_7292_hiresjpg.jpg
  4. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/Table.jpg
  5. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/bigstock-Businessman-using-a-digital-ta-209395744.jpg
  6. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/bigstock-Architects-Working-On-Blueprin-229082437.jpg
  7. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/bigstock-Pointing-4995603.jpg
  8. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/bigstock-198722974.jpg
  9. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/bigstock-business-people-architecture-85687487.jpg
  10. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/Keith-Robinson.jpg
  11. krobinson@dialogdesign.ca: mailto:krobinson@dialogdesign.ca
  12. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/Cam-Franchuk.jpg
  13. cfranchuk@dialogdesign.ca: mailto:cfranchuk@dialogdesign.ca
  14. [Image]: https://www.constructioncanada.net/wp-content/uploads/2018/12/Gerald-Murnane-DIALOG.jpg
  15. gmurnane@dialogdesign.ca: mailto:gmurnane@dialogdesign.ca

Source URL: https://www.constructioncanada.net/assignment-of-design-to-constructors-a-discussion-and-direction/